Saturday, 22 February 2014
PCI and Handover Dates
Emailed my SS this morning and asked if he was able to provide a estimated PCI or settlement date, which he replied back in no time (let me work it out and will get back to you today). Within an hour he replies back with the scheduled time frame for all remaining jobs and a date for PCI, and settlement day. Thanks to the SS, great guy with no hassles.
PCI will be on Thursday the 27th March
Settlement/handover will be on Thursday the 10th of April
10th April 2014 - Settlement and Handover
According to the eden brae online website status our house is on completion stage now with the followings:
Painting, wall and floor tiling is currently being completed. All electrical, plumbing, heating and vacuum systems will be fitted off (where applicable). Shower screens, mirrors and splashbacks, door furniture, robe rails etc. will be installed. Once all these items have been complete then the Practical Completion Stage is then complete.
Your site supervisor will contact you to arrange a practical completion inspection.
A progress payment invoice will be provided for authorisation by the client and/or the lending body.
Your bank or lending institution has requirements that need to be met for funds to be released for contract settlement. You will need to contact your lender for further details.
Client Checklist
Your site supervisor will contact you to arrange a practical completion inspection.
You need to authorise the progress payment invoice for this stage it and forward it to your lending institution for payment within 7 days.
Your bank or lending institution has requirements that need to be met for funds to be released for contract settlement. You will need to contact your lender for further details.
06th February 2014 – Lockup Completed / LININGS Stage Now Started
Just paid brick invoice only a day or two ago and this morning another invoice for LININGS was delivered in my email box, thanks to the technology. I was under the impression that all invoices will be paid upon completing the jobs and I kind of jumped on my seat saying OMG speedy work done by EBH looks like we need to start packing soon, but I was wrong because linings invoice was to be paid before the commencement of this stage – what a shame, huge amount to pay for something which has not been delivered. Spoke with the bank and they had no issues paying as long as I am happy to repay hahaha – but bank will not release the last payment which will be the next one, until bank has done the final valuation and insurance taken for a amount agreed with the bank to cover any loses with the property.
Spoke with the accounts department at EBH and they were happy to have this invoice paid upon completion because she thought this stage will be completed by early next week anyways and happy to accept payment late next week. But I still asked my back to pay the half of the invoice amount in case and half will be paid next week once linings stage is complete.
Also visited site last night, but did not find much difference or updates. No eaves yet and most importantly SS is still missing as I have not heard from him from last 2 weeks. I believe he is still on holidays and due back Monday next week.
A few things happened in last 48 hours after my last visit which was on Tuesday the 4th. Today visited again and and found the electrical work was fully completed, Insulation was done in the entire house, Architraves around the windows were also done, Gyprock and Cornices were delivered as you can see in the main living room and most importantly Bricks on some parts of the house were also cleaned and they now look very neat and clean. Linings invoice was also paid yesterday which was issued just one day after I paid bricks invoice.
Garage
Study
Main Bedroom
Entrance
Living Room
Living with Kitchen
Bed Rooms
Rumpus
Cornices
Clean Bricks
Alfresco